"Yashima-san, it's always during crises that I see you, but I'm genuinely pleased to have you here," remarked the Turnaround Manager of the Taiwanese state refinery during the emergency shutdown this March.

This urgent project required immediate intervention. The failure of hand-welded V-anchors, coupled with the absence of protective refractory material, resulted in significant shell damage. Our partners at Taiwan CoreTech Inc. reached out to us for a swift response.

Scope of work

We received a call on Friday, March 21, 2025. By March 22, our crew was mobilized.
The D-20 machine was already stationed in Taiwan, and we promptly shipped the SpeedVees® anchors. Our team comprised three members: two RAW Operating Supervisors and one Project Manager.

For the SILICON crew, the emergency job at the Resid Fluid Catalytic Cracking (RDCC) Unit was straightforward. We executed patch repairs using SpeedVee® refractory anchors, with precise marking in specific areas to establish patterns within the patches. Three days later, the crew was ready for demobilization.

The site was truly multinational, with Dutch, Japanese, Taiwanese, and Malaysian employees collaborating seamlessly. This diverse team utilized Rapid Arc Welding (RAW), a universally comprehensible method that transcends cultural barriers. As a result, the customer was thoroughly impressed with the results.

As Tomomi Yashima aptly stated,
"We were there to provide top-notch quality service, and we did."

Emergency Response Experts

With four decades of experience in refractory anchor production and installation, we confidently assert that Rapid Arc Welding (RAW) is unparalleled in emergency situations. Our team consistently showcases exceptional skill and efficiency in managing urgent scenarios, ensuring our clients receive superior service even under the most challenging conditions. Whether it's a sudden shutdown or a critical repair, our industry expertise and RAW technology enable us to deliver swift and reliable solutions.

SILICON Total Solution Provider

No matter how challenging your emergency repair needs are, having SILICON on site makes a huge difference. Our Rapid Arc Welding (RAW) technology ensures consistent, reliable welds without power loss, as the technology compensates for it. With cable lengths of up to 200 meters, there's no need to relocate machines across different levels, enabling efficient operations at various heights. This saves time and resources.

The SILICON Emergency Project Team, along with our in-house engineers and RAW technology, will transform your high-stakes environment into a controlled repair process.

Emergency? We are here for you.

Do you know someone in an emergency?

Share our contact with them: raw.projects@silicon.nu

We're available 24/7 to provide the support and solutions they need during critical times.

At this jobsite

  • Emergency repair – fast mobilization
  • Anchors/solution: SpeedVee®
  • Areas: Resid Fluid Catalytic Cracking Unit
  • Installation Time: 24 March – 26 March 2025 (3 days)
  • 3 Crew Members: 1 Project Manager, 2 RAW Operating Supervisors
  • Machines: 1xD20